top of page

I-70 Wall Replacement

Eagle County - Colorado

Owner - Colorado Department of Transportation

Contract amount - $4,174,000

Start - May 2024

Estimated Completion - Fall 2024

The Colorado Department of Transportation and prime contractor, Siete Inc., will begin a wall replacement project along westbound I-70 in Dowd Canyon on Monday, May 6. Work will take place from Mile Marker 169.5 to MM 171.5 in Eagle County between Eagle-Vail and West Vail. Crews will remove portions of the existing earth wall above US 6 at MM 170.5 and replace it with a new Mechanically Stabilized Earth (MSE) wall. Additional light paving, guardrail installations, striping and electrical work will also take place through the project zone. The project will not only protect the future integrity of the roadway, but will also enhance the aesthetics of the corridor for a safer and more enjoyable driving experience.