Current & Upcoming Projects
Aguilar Reservoir
Las Animas County - Colorado
Owner - Town of Aguilar
Contract amount - $2,088,000
Start date - November 2023
Estimated completion - Spring 2024
This project is to provide a new reservoir for water storage purposes with associated earthwork, infrastructure, and restoration. This project more specifically involves the following 1. Site Grading and Access 2. Ditch cleaning, grading, regrading, or filling 3. Demolition and abandonment of existing facilities. 4. Mass excavation 5. Various pipe- works for underdrain, discharge, or bypass pipelines 6. Relocation of overhead power. 7. Installation of infrastructure elements such as release gates and manholes 8. Bentonite and other “liner” practices using native soils and import additives 9. Finished grading and restoration.
Cottonwood Creek Rehabilitation
El Paso County- Colorado
Owner – City of Colorado Springs
Contract Amount - $5,900,00
Estimated completion – Spring 2023
Following significant erosion of Cottonwood Creek, Colorado Springs received a FEMA grant to restore the creek. Siete, Inc. was hired as the prime contractor for the construction of concrete drop structures to slow with flow of water through the creek, stabilizing the floor of the channel to prevent further and future erosion. The project also included sheet piling and embankment.
Grandview Bridge Replacement
Fremont County - Colorado
Owner - Fremont County
Contract amount - $3,115,700
Start - May 2024
Estimated Completion - Fall 2024
Siete, Inc. was awarded the Grandview Ave. bridge replacement project by Fremont County in March. The project consists of removing and replacing the current bridge over a portion of the Fourmile Creek, east of Steinmeier Ave. The original bridge was built in 1940 and was reconstructed in 1965. The average daily traffic over the bridge is 1,541. The project is expected to last six months.
Grizzly Reservoir Dam Rehabilitation
Pitkin County - Colorado
Owner – Twin Lakes Reservoir
Contract amount - $3,946,800
Estimated project start - Summer 2024
Siete, Inc. was hired by Twin Lakes Reservoir and Canal Company as the prime contractor for the Grizzly Reservoir Dam rehabilitation project that will replace the gates that control water flow , repair the outlet that works to release water to Lincoln Creek, reconstruct embankment and construct a retaining wall at the Twin Lakes tunnel intake.
I-25 & CO 12 Critical Culvert Repair
Huerfano and Pueblo County - Colorado
Owner - Colorado Department of Transportation
Contract amount -
Start date - February 2024
Estimated completion - Summer 2024
This project entails repairing culverts that are in critical condition along the southern route of Interstate 25 and Colorado Highway 12. There are four locations on I-25 between Pueblo and the New Mexico border with three additional locations on CO 12 between La Veta and Trinidad. All culverts are in immediate need of repair, which includes new linings, headwalls and concrete reinforcements.
I-25 Walsenburg Bridge Replacement
Huerfano County - Colorado
Owner – Colorado Department of Transportation
Contract Amount - $19,259,072
Estimated project state - spring 2023
Estimated Completion – Spring 2024
Siete, Inc. was awarded the I-25 Bridge Replacement project that will rehabilitate the existing I-25 northbound bridge and replace the existing southbound bridge. The bridges traverse railroad tracks as well as CO 10 and US 160. The project will also require adjusting the grade of the roadway.
I-70 Wall Replacement
Eagle County - Colorado
Owner - Colorado Department of Transportation
Contract amount - $4,174,000
Start - May 2024
Estimated Completion - Fall 2024
The Colorado Department of Transportation and prime contractor, Siete Inc., will begin a wall replacement project along westbound I-70 in Dowd Canyon on Monday, May 6. Work will take place from Mile Marker 169.5 to MM 171.5 in Eagle County between Eagle-Vail and West Vail. Crews will remove portions of the existing earth wall above US 6 at MM 170.5 and replace it with a new Mechanically Stabilized Earth (MSE) wall. Additional light paving, guardrail installations, striping and electrical work will also take place through the project zone. The project will not only protect the future integrity of the roadway, but will also enhance the aesthetics of the corridor for a safer and more enjoyable driving experience.
Medal of Honor Boulevard Extension
Pueblo County - Colorado
Owner - Pueblo County
Contract amount - $33,438,500
Start - May 2024
Estimated Completion - Fall 2025
As the only Pueblo County contractor bidding the project, Siete, Inc. was extremely excited to be awarded the project in April. The project is located between the S. Joe Martinez Blvd & Purcell Blvd. intersection in Pueblo West and the Pueblo Blvd. & 24th St. intersection in Pueblo. Medal of Honor Blvd will cross over the Wildhorse Creek arroyo and through the Honor Farm Open Space in Pueblo. The roadway extension will improve traffic flow by providing additional access between Pueblo and Pueblo West. The project will also enhance economic opportunities in the area. Medal of Honor Blvd will provide access to the new Pueblo County jail facility.
Nichols Road Reconstruction
Pueblo County - Colorado
Owner – FHWA
Contract Amount - $4,417,577
Estimated project start - Jan 2023
Estimated Completion – Summer 2023
Siete, Inc. was awarded the FHWA project that will reconstruct Nichols Road from the McCulloch intersection to the bridge. The reconstruction will include widening the intersection to accommodate left turning vehicles, building a trail addition that will link to Pueblo West High School, construct a grade separated pedestrian bridge over the railroad tracks, along with resurfacing the roadway.
Queen Dam Outlet Works Replacement
Kiowa County - Colorado
Owner - Amity Mutual Irrigation Company
Contract Amount - $1,973,000
Estimated Project Start - Summer 2024
Estimated completion - Fall 2024
Queen Reservoir Dam, a 35,657 acre-foot reservoir, has been under a storage restriction since July 2017. The reservoir rehabilitation project will remove the safety restriction and allow continued delivery water to shareholders for irrigation. Queen Reservoir is located in Kiowa County, approximately 12 miles north of Lamar. The rehabilitation project includes the removal of entire outlet works and replacement of the outlet works components of the dam, as well as replacing the headwall with an earthen embankment.